- Location – Bicholim, Goa, India
- 30 MW steel waste heat recovery power plant
- Fuel – coke oven fired gas and blast furnace gas
- Consultant – Fichtner Consulting Engineers (India) Pvt. Ltd.
- Boiler – 2 WHRB, 89 kg/cm2, 520°, 65 TPH
- 30 MW bleed condensing steam turbine
- Type of condenser – air cooled condenser
- Project commissioned in 2012
WASTE HEAT RECOVERY POWER PLANTS
Thermax has been at the forefront of the waste heat recovery power plant for more than a decade. Our portfolio of over 500 MW of waste heat recovery projects reaffirms the customer's preference for our solutions.

Steel
Customer - A Mining Company based in India